The mine will be fully mechanised and SRK has proposed a ramp access to the orebody with mining by a sub level caving system for ore production of 700,000 tons per annum giving a projected mine life of 25 years. Mined grades delivered to the beneficiation plant have been estimated at 43.7% Cr2O3 after mine recovery and dilution factors have been applied. Mintek has provided process options to produce a number of saleable chromite ore products. The plant would comprise crushing, milling, dense media separation and gravity concentration units with sufficient flexibility to allow high grade ore to be crushed and screened to form a metallurgical ‘lumpy’ product should selective ore mining prove feasible.
It is expected that the proposed plant will be able to produce two products, namely a metallurgical ‘lumpy’ product grading approximately 49% Cr2O3 and a metallurgical fines concentrate grading approximately 55% Cr2O3. Estimated total annual sales are expected to be in the order of 511,000 tons split approximately as to 322,000 tons for the ‘lumpy’ material and 189,000 tons for the fines concentrate.
Marketing data supplied by Heinz Pariser has indicated that the sale price of chrome ore products from Kazakhstan during the first quarter 2005 have ranged from US$142 to US$200 per ton. Oriel is in discussion with a number of interested consumers of the Voskhod products both in China and Russia and will be pursuing these markets aggressively over the coming months.
Pre-production capital costs have been estimated at US$48 million prior to initial revenues from chromite production. This estimate does not include financing, administration and taxation costs. Cash operating costs over the life of the mine have been estimated at US$24.8 per ton of ore mined which equates to a cash cost of US$34 per ton of chromite product sold, based on an assumed yield of 73% saleable products from the run of mine ore. The project NPV, pre financing charges and government taxes, at a chromite sale price of US$170 per ton and a 10% discount rate is given as $329 million with an IRR of 62%. The range of NPV’s and IRR’s at chromite sale prices of US$142 and US$200 per ton are US$212 million at 46% and $454 million at 78% respectively and indicate extremely robust project economics.
Our advisors, Endeavour Financial, have provided Oriel with early confidence that it is likely that project debt funding of up to US$40 million could be available to finance the development of Voskhod. The level of Oriel’s cash reserves and the amount of potential debt financing places Oriel in a position where it does not envisage any requirement for further equity raising for the development of Voskhod.
The SRK report has provided Oriel with sufficient confidence to proceed to the next stage of project development, notwithstanding a Definitive Feasibility Study (DFS) is yet to be completed. SRK, as lead engineer, is preparing a detailed proposal to undertake the DFS for completion by 2nd quarter 2006 in conjunction with Mintek on process testwork and design and an internationally recognised process engineering company. As part of this fast track process Oriel has decided to commence the design and construction of the access ramp to the Voskhod orebody and has commissioned SRK to prepare detailed designs for the ramp and associated development works for submission to the relevant Kazakh authorities for approval to start engineering works during 2nd quarter 2006.
Oriel confidently expects production of chromite ore from the Voskhod deposit to commence mid 2007.
Shevchenko
Further to earlier announcements Oriel now expects that the completion of the Definitive Feasibility Study (“DFS”) will be completed in early 2006. The timetable for the completion of the DFS has been pushed out by delays in receiving final tenders and re-engineering work on some of the more complex production and infrastructure models.
This revised timetable has not impacted on progress in other areas and Oriel with its advisor Endeavour Financial, has short listed a number of multilateral and commercial international banks. Indicative term sheets for their participation in funding the debt portion of the Shevchenko project are currently under review.
In addition, Oriel continues to receive excellent support from both the regional and the Federal Government in Kazakhstan for both Voskhod and Shevchenko and this is expected to continue, as the projects develop, into material assets for the company.
_______________________________________________________
Dr Alwyn Annels, PhD, CEng, FIMMM is a Principal Mining Geologist at SRK (UK) Ltd, and was co-author of the Preliminary Assessment Study. He is a qualified person in accordance with definitions set out in National Instrument 43-101 and he has consented to this announcement and reference to his report herein.
Mr Mike Beare, BEng, CEng, MIMMM, Senior Mining Engineer at SRK (UK( Ltd), and was co-author of the Preliminary Assessment Study. He is a qualified person in accordance with the definitions set out in National Instrument 43-101 and he has consented to this announcement and reference to his report herein.
ENDS
For further information, please contact:
Dr Sergey V Kurzin, Executive Chairman, Oriel Resources plc
Tel: +44 (0) 20 7514 0590
Dr Nic A Barcza, Managing Director, Oriel Resources plc
Tel: +44 (0) 20 7514 0590
Nick Clarke, Director of Mining, Oriel Resources plc
Tel: +44 (0) 20 7514 0590
Jonathon Brill/Billy Clegg, Financial Dynamics
Tel: + 44 (0) 20 7831 3113
Vanguard Shareholder Solutions
Tel: 1-800 866-788-9288
