The process route selected considers the initial construction of two 80MW DC-Arc furnaces followed by the construction of a third furnace in year three of operations. Pyrometallurgical recoveries are expected to be 92 per cent into a refined ferronickel product grading 22 per cent nickel. Annual refined ferronickel production from year five is expected to be about 140,000 tonnes per annum containing 31,000 tonnes of nickel.
In addition, Oriel has commissioned consultants Brook Hunt to provide information as to likely consumers of the ferronickel product. They estimate that stainless steel output will increase by 3.3 per cent per year over the next ten years and that both Europe and China may be ready markets for the Shevchenko ferronickel product.
Also as part of its programme towards a full bankable feasibility study, which it plans to complete next year, Oriel has shipped a 450 tonne bulk sample of Shevchenko ore for testwork at Mintek, South Africa in their 2MW DC Arc furnace which is programmed to commence in November. A further 35 tonne sample of nickel ore has been shipped for drying and calcining test work at Polysius, part of the ThyssenKrupp Group, Germany and testwork is currently in progress. Oriel is in negotiations with three major international technology and equipment suppliers for assistance in preparation of the feasibility study, project financing and possible future off-take agreements for the ferronickel products. Oriel will be appointing its chosen technology and engineering partners by November 2004.
On a recent visit to Kazakhstan by Oriel’s Directors and a number of analysts from the UK and Canada, meetings were held in Zhitigara, Kostanay and Astana with senior Government officials at the local and federal levels. These meetings demonstrated and confirmed full central government support for the Shevchenko Project and the company’s activities in Kazakhstan. Further to these meetings Oriel is currently negotiating potential tax concessions and privileges in line with current legislation of Republic of Kazakhstan which could substantially improve the post tax project economics. In addition, Oriel is in the process of negotiating with potential suppliers of electricity, gas and rail links to the project site for them to provide the capital infrastructure requirements in return for long term supply contracts which may substantially further reduce initial capital commitments.
Executive Chairman Dr Sergey V Kurzin said "Today's study fully justifies the enthusiasm of investors when we came to the market in March. We have the advantage at Shevchenko of an existing infrastructure with good transport links, low cost power, gas and labour and other readily available resources that means we should be able to complete and operate the Project very competitively. Now that the resource has been shown to be viable we plan to press ahead vigorously in order to deliver value to our shareholders."
For further information please contact:
Dr Sergey V Kurzin
Executive Chairman and CEO
or Stephen R Dattels
Managing Director
Tel: 020 7514 0590
